On 27 January, using the opportunity of the InterOPERA General Assembly taking place in Berlin, RTE visited GE laboratory. The visit included the showcase of the current status of the cubicles being prepared for Factory Acceptance Testing, which is scheduled for completion by the end of March.
In addition, RTE and TUD also took the opportunity to visit the HIL (Hardware-in-the-Loop) laboratory at GE Grid Solutions GSI (gas insulated substation). The technical team presented the progress of their work and discussed next steps to ensure the readiness of the GSI replicas for the Factory acceptance tests in March.